Case Study: Procurement Project Management using Competitive Dialogue
Client: Royal Borough of Kingston upon Thames
Confian brought a great combination of skills to the project.’ Karl Limbert, Head of Property Royal Borough of Kingston.
Kingston’s Challenge: Urgent replacement of Project Manager for Strategic TFM procurement
When the Royal Borough of Kingston upon Thames had unexpectedly lost their in house Project Manager, in the middle of a Competitive Dialogue procurement, Head of Property, Karl Limbert, commissioned Confian for help
As a Council, they had no previous experience of Competitive Dialogue. He knew of our work, having been on the client-side at previous local authorities, where we had supported bid teams. Within two weeks, we had deployed Terry Mitchell into the role, managed a three week handover with the in-house team and immediately began preparation for the Call for Final Tenders.
‘I had known Terry for his work in leading bid teams on large strategic procurements and had full confidence in his ability to provide the urgent support we needed. His local government knowledge and private sector bidding experience brought a great combination of skills to the project.’ Karl Limbert, Head of Property Royal Borough of Kingston.
What we did
- Reviewed the existing project documentation
- Researched the detail of the Council’s standing orders and procurement procedures to flush out all potential procedural risks and issues to the project.
- Worked with each work stream leader to establish the constraints and challenges of meeting the timetable.
- Worked with external legal advisors Sharpe Prtichard and technical advisors Deloitte, to manage the production of the procurement documentation ready for the Call for Final Tenders.
- Facilitated and managed the preparations for the Competitive Dialogue meetings with shortlisted bidders, including pre and post briefing meetings with the Council’s Team.
- Managed and advised on responses to clarification questions raised by Bidders
- Supported the procurement professionals in the Council, working through the mechanics of the Competitive Dialogue process, including the evaluation team briefing, challenging the evaluators’ conclusions and supporting the preparation of the Preferred Bidder letter.
- Supported the production of the Council’s committee report and recommendations for award of the contract which was approved by Council Members
- Managed the Preferred Bidder stage process of clarification.
- Established the Council’s mobilisation team and guided them through the production of a formal Project Initiation Document, Project Plan, Risks and Issues log and Communications Plan.
- Managed the initial stages of the Mobilisation phase and handover to the Council’s client team and supported the liaison activity with Cofely (part of GDF-Suez/Engie Group), the selected Service Provider
- Worked with the Council’s HR team to support the TUPE process, including staff focus groups, liaison with unions and staff representatives, and formal TUPE consultation on Measures
The challenges we faced and how we overcame them:
Parachuting into an existing team is always a challenge, especially in the fast moving timetable of a major procurement. Adapting to the team culture, understanding processes, delivering to the next deadline, were all part of what we faced. Using our knowledge of the local government culture and the demands of the bidding process, we quickly established a new timeline for the project, respecting the key milestone dates that had already been set, especially the ‘Go-Live’ date.
Key relationships were quickly built especially with the Procurement professionals, with whom we worked closely, to understand the detail of the Council’s own processes and procedures as well as the demands of the Competitive Dialogue process.
‘Working with an organisation that has worked both sides of major bids is invaluable. Confian’s knowledge of the practicalities of the Competitive Dialogue process and understanding what was happening on the bidders’ side, helped us to confidently manage the procurement.’ Chris Morgan Head of Commissioning Royal Borough
The Outcome?
- Successful procurement and selection of a Preferred Bidder, on time
- Contract signature signed by the date agreed between the Client and Contractor
- Successful preparation for Mobilisation project and handover to the Client in-house team